/RPM/PLMPS_UPLOAD - PLM PS project upload
Fill RESBD Structure from EBP Component Structure SUBST_MERGE_LIST - merge external lists to one complete list with #if... logic for R3upThis documentation is copyright by SAP AG.
Functionality
This FM is used for uploading a project from PLM PS Project system to the xRPM system. For uploadinga project from the PS system, an approved proposal/project has to be created in xRPM system. The projectupload from the PS system will copy the tasks from the PS system to the xRPM system and also update some of the project fields.
During the upload some of the fields in xRPM project is updated from the PS project. The project fields like Plan Start and Plan Finish, Description etc are changed.
The tasks are either Updated, Inserted or deleted after checking with the tasks in the xRPM system.If a task coming from the PS system does not exist in the xRPM system then this is Inserted. If a taskexist in the xRPM system and if it is not returned from the PS system, then this is deleted in the xRPM system. The decision for Update is taken by comparison of some specific fields between the PS and the xRPM system.
All the objects are updated, inserted, deleted in the buffer and finally saved by the Object manager.
Example
Notes
Further information
Parameters
ET_MSGEV_RC
IV_CHANGE_RESOURCE
IV_CHANGE_ROLE
IV_CHANGE_TASK
IV_CHANGE_TEAM
IV_EXTERNAL_ID
IV_LANGUAGE
IV_LOGSYS
IV_PORTFL_ITEM_GUID
IV_PS_PROJECT_ID
IV_SIMULATION
Exceptions
Function Group
/SAPLINTEGRATION_PLMPSFill RESBD Structure from EBP Component Structure General Data in Customer Master
This documentation is copyright by SAP AG.