C_PROJ_VNR - PS: Project Manager for Project Definition
PERFORM Short Reference SUBST_MERGE_LIST - merge external lists to one complete list with #if... logic for R3upThis documentation is copyright by SAP AG.
Definition
You can use this authorization object to control who has access to the project definition in the Project System depending on the person responsible for the project ("project manager").
The system checks the authorization:
- during maintenance (editing transactions)
- during display
Defined fields
The authorization object contains the following fields:
- Number of the person responsible for the project definition
- Action
The following values are used for the actions:
- 01: Create
- 02: Change
- 03: Display
- 45: Change project number
The field for the project manager has eight places. Enter a number for the project manager with leading zeros. For example, 23: "00000023".
Examples
User A may change the project definition L-400, that is assigned to project manager D002852. Relevant authorizations:
- Project manager number: D002852
- Action: 02
CPI1466 during Backup CL_GUI_FRONTEND_SERVICES - Frontend Services