KJ314 - Create a cost element for revenue in excess of billings - KJ 314

PERFORM Short Reference   ROGBILLS - Synchronize billing plans  
This documentation is copyright by SAP AG.
SAP E-Book

Diagnosis

If you are using the POC method to perform results analysis, the system computes the calculated revenue by multiplying the percentage of completion by the planned revenue. If the calculated revenue exceeds the actual revenue, the system creates revenue in excess of billings.

The revenue in excess of billings is written under a results analysis cost element.

System Response

Procedure

  1. Create a results analysis cost element for the revenue in excess of billings.
  2. Go into Customizing and enter the results analysis cost element in the results analysis version.





BAL Application Log Documentation   General Material Data  